The Problem:
Alston Construction and Witech Excavating needed to expedite Project Heartland to guarantee their building pad would be completed before winter. Wet fill and cooler temperatures put their project schedule at risk.
The Solution:
Using Soil modification with quick lime, dried the wet fill to meet compaction requirements.
Capping the building pad with cement stabilization, protects it from Old Man Winter.
In 19 days over 520,000 SYs of wet fill were treated with quick lime (that’s over 27,000 SY’s per day)
In 6 short days the building pad was cement stabilized to beat the schedule (that’s 25,000 SY’s per day)
We want to recognize Alston Construction and Witech Company for choosing to build smarter, build faster, & build better.